Brown Line Work Delayed; Dates Emerge

By vouchey in News on May 13, 2005 4:59PM

Belmont PlatformScooping the Trib, the Sun Times reports today that the CTA planned on beginning Brown Line construction this month, but because of delays in procuring property adjacent to the stations, will not begin work until September.

Chicagoist has dealings with CTA now and then, and knows it recently restructured its real estate department. In recent months a number of staff have been moved out, and at least one department general manager has been changed. While it's hard to say if the staff shuffles are the cause of purchasing delays, they probably don't help.

Using information gleaned from today's Sun Times report, along with a schedule posted by CTA a few months ago, here's the closure schedule Chicagoist expects:

Reported Contruction/
Closure Begin Date
Stop Expected Opening
Mid-August 2005 Belmont No closure
Fullerton No closure
Sedgwick Closed 6 weekends
Armitage Closed 6 weekends
Chicago Closed 6 weekends
Later this year Western No closure
December, 2005AddisonOctober-December 2006
MontroseOctober-December 2006
February 2006SouthportDecember 2006-February 2007
DiverseyDecember 2006-February 2007
August 2006KimballJanuary-March 2007 + 10 Weekend Closures
FranciscoMarch-May 2007 + 10 Weekend Closures
January 2007Irving ParkNovember 2007-January 2008
DamenNovember 2007-January 2008
Spring 2007PaulinaSpring 2008
Late 2007WellingtonLate 2008

Image via Chicago-L.org.